The client decided to use a different MRI than what was originally picked for the project. This required a reworking of the layout in this area and in the clearances required for accessibility to the changing room and toilet. Phasing of construction was very important, as was ensuring that the MRI installation did not cause any significant changes to the exterior of the building per the association.
Further work included relocating the Physical Therapy from the first floor to the second and adding a conference room, private offices and doctors’ offices on the first floor.